In 2013, the Texas Department of Transportation (TxDOT) started the reconstruction expansion of FM 2234 from Cartwright Rd. to the Fort Bend Tollway. Initially, this roadway project was to be 11 months; but over the course of a year, the project is estimated to be complete by June 2015 (weather permitting). The FM 2234 expansion project will include a 4-lane highway (curb and gutter section with a raised median).
According to the Texas Department of Transportation (TxDOT), the segment between the Fort Bend Tollway to FM 521 (Almeda Rd.) is slated for bid next month. Moreover, they estimate this expansion project to begin later this calendar year (December 2015). As soon as a commencement date is announced by TxDOT, Council Member Green will facilitate an informational meeting at least 2 weeks prior to inform and better prepare the adjoining communities about the proposed projects. Stay tuned.